Case from the Court of Appeal for England and Wales concerning a developer’s claim for damages against a consulting engineer who failed to perform tasks by an agreed date. The developer (a farmer) sought damages in respect of the fall in the value of his development (due to the property slump) during the period of the delay.
In terms of an oral agreement (followed by a formal letter of engagement) reached with the developer on 6 September 2006, the engineer was to design a road and drainage to the developer’s site and to obtain s38 approval (allowing adoption of the road by the roads authority in terms of the Highways Act 1980) by March 2007. An initial s38 approval was not obtained until 17 February 2008 and even then some parts had not been finalised. In April 2008 the developer engaged another consulting engineer who obtained the necessary approval in June 2008. The judge found that the first engineer’s breach of contract delayed the development by 15 months and that had resulted in loss to the developer because of the reduced value of the development.
The question for the appeal court was whether the developer’s loss was too remote to allow recovery. The appeal court dismissed the engineer’s appeal agreeing with the judge’s finding that that the loss was not too remote as it was reasonably foreseeable as a serious possibility if there was a delay. It also agreed with the judge’s finding that the case was not one of the unusual cases where the nature of the contract and the commercial background, or other relevant special circumstances, mean that an implied assumption of responsibility for losses that can be reasonably foreseen was inappropriate.
The Court of Appeal’s comments on the length of delay are also worth noting:
“It may well be that the reason for the absence of many cases of this kind is that the property market does not move as quickly as certain other types of market involving commodities and other goods, and it takes a very lengthy delay in breach of contract before a provable loss of value can occur. A few days or even a few weeks delay is unlikely to give rise to a demonstrable loss on the property market. It was the appellant’s delay of 15 months, in the Judge’s words an egregious delay, which in the present case gave rise to a quantifiable loss.”
The full judgement is available from BAILII here.