Sheriff Court case concerning liability for the maintenance of Carbeth House in Killearn. The property comprised 9 flats each of which was subject to a deed of conditions.
Facts
A large crack which appeared in the west wall of the property on 16 August 2007 was examined by a building standards surveyor from Stirling Council on 17 August 2007 and found to be dangerous. The surveyor wrote to the owners of the flat requiring a protective fence to be erected around the wall and intimated that a dangerous buildings notice would be served on the owners by the Council. On the recommendation of a civil engineer and, following a majority vote of the proprietors (by email), a protective fence was erected together with scaffolding to support the wall (on 20 August 2007).
The crack in the wall was discussed, and the measures taken, explained at a meeting of the proprietors on 23 August 2007 (convened primarily to discuss another matter) and no objection was raised. A dangerous buildings notice was issued to the proprietors on 24 September 2007. Contractors were asked to tender for the repair works required by the dangerous buildings notice and, in September 2008, the proprietors voted by majority (again by email) to accept one of the tenders.
The proprietors were then asked to contribute money into a repair fund. However, Mrs Wallace and Mr Crossan declined to contribute. After some legal correspondence, solicitors acting for Mrs Wallace and Mr Crossan indicated in a letter (on 29 May 2009) that they would pay their share of the costs of the repairs on receipt of the appropriate engineer’s certificate and were anxious for the work to be carried out and the scaffolding removed.
In June 2009 the repair commenced. The repairs, along with additional works revealed as necessary when the initial work began, were completed on 12 October 2009. Mrs Wallace and Mr Crossan failed to pay their share of the costs and Mrs Garvie was authorised by a majority vote of the other proprietors to recover the sums due from Mrs Wallace and Mr Crossan.
Argument
Mrs Wallace and Mr Crossan argued that the sums could only be recovered if the works had been done in terms of the title deeds. In terms of the deed of conditions there had to be a meeting of the proprietors before works could be instructed (and, they argued, no scheme for works had been agreed at the meeting on 23 August 2007).
Decision
The sheriff found Mrs Wallace and Mr Crossan were liable to pay their share of the cost of the repairs (£6,483 in the case of Mrs Wallace and £6,858 in the case of Mr Crossan). He concluded that the wording of the deed of conditions was permissive and that the procedure in the deed of conditions was not the only method by which the proprietors could instruct repairs. Against that background the sheriff considered the situation by reference to the common law, consent and the Tenements (Scotland) Act 2004.
Common law
The wall was common property and, in terms of the common law, all of the proprietors were obliged not only to contribute towards the cost of the repairs but to actively ensure that the repairs were carried out. It is also a well known principle of the common law of common property that any one proprietor can instruct common repairs and then look to fellow co-proprietors for a contribution towards the cost. Quite apart from the deed of conditions, the sheriff took the view that all of the repairs were necessary and could be instructed by any of the co-proprietors and that Mrs Wallace and Mr Crossan were obliged to pay a share of the costs.
Consent
With regard to consent, Mrs Wallace and Mr Crossan had attended the meeting on 23 August 2007 at which the works and costs had been discussed and made no objection. The letter of 29 May 2009 could be treated as unconditionally binding Mrs Wallace and Mr Crossan to the costs including the increased costs and additional work. Even if not, they had been provided with information at each stage and were to be deemed to be renewing the authority given in the letter by failing to revoke it.
The Tenements Act
Initial scaffolding works
With regard to the Tenements (Scotland) Act 2004, the initial scaffolding work amounted to an emergency repair[1] and, as the deed of conditions did not provide for emergencies, the tenement management scheme contained in the 2004 Act applied. Any owner can instruct emergency repairs and the costs of such work are “scheme costs” (meaning they would be shared[2] amongst the proprietors).
Retention of the scaffolding
As to the retention of scaffolding in place after the meeting on 23rd August 2007, the procedure for making the decision to do so was provided in the deed of condition (i.e. by majority vote at a meeting of the proprietors). In this case the meeting had not been convened in accordance with the deed and there was no vote. However, there had been a meeting at which it was discussed and the proprietors knew the scaffolding would need to remain in place until repairs could be organised. There was no evidence that Mrs Wallace and Mr Crossan had disputed the need to retain the scaffolding and there had been consensus amongst the proprietors at the meeting. As such, the sheriff found that a scheme decision had been made (in terms of the 2004 Act) but that the decision had been reached by an irregular procedure[3]. However, the irregularity did not affect the validity of the decision[4].
Completion of the works
The same analysis applied to the repairs carried out. A vote took place by email after circulation of the projected scheme costs. The majority approved the scheme and, even though Mrs Wallace and Mr Crossan may not have voted in favour of the scheme, they did consent. Again, although this did not follow the procedure contained in the deed of condition, the sheriff found that there had been a valid scheme decision (albeit reached by an irregular procedure).
The full judgement is available from Scottish Courts here.
All of our property and conveyancing case summaries are contained in the LKS Property and Conveyancing Casebook here.
[1] Rule 7 of the Tenement Management Scheme provides that emergency work includes work which is required to prevent damage or in the interests of health or safety (and the sheriff considered that the erection of the scaffolding satisfied both of those criteria).
[2] In this case the proportions in which the costs were shared were governed by the deed of conditions.
[3] As it had not followed the procedure contained in the deed of conditions.
[4] Rule 6.1 of the Tenement Management Scheme provides that “any procedural irregularity in the making of a scheme decision does not affect the validity of the decision”.